Driveway Cleaning Calculator

Estimate time and resources for driveway cleaning by area and surface type.

Pressure washer flow rate

Seal after cleaning

Sealing recommended for block paving

How We Calculate This

How the calculation works

Cleaning time is calculated from the driveway area and coverage rate for the surface type.

Coverage rates (m² per hour)

  • Concrete: 7 m²/hr
  • Block paving: 5 m²/hr
  • Tarmac: 8 m²/hr
  • Resin-bound: 10 m²/hr
  • Imprinted concrete: 6 m²/hr

Formulae

Area = length × width

Time = area ÷ coverage rate

Water = time × flow rate × 60

Sealant = area × 0.15 L/m²

Frequently Asked Questions

Last updated: February 2026

All calculations are estimates. Always verify quantities and timings for your specific situation.